URA Home
A research consortium of The Texas A&M University System and The University of Texas System

Senior Technical Review Report February 1996


Comments on the Overall Fissile Materials Disposition Program, and Three Elements of that Program: Immobilization Alternatives, Joint U.S./Russian Programs, and Deep Borehole Disposition

The Senior Technical Review Group met to consider and comment on the overall Fissile Materials Disposition program, and three elements of that program: Immobilization Alternatives, Joint U.S./Russian Programs, and Deep Borehole Disposition.

After extensive briefings and discussions on February 1 and 2, the Group made the following recommendations and observations:

Overall Fissile Materials Disposition Program

The group urged DOE to pay more attention to the timeliness factor, to ensure that timeliness is balanced with other considerations at each step of the decision making process. DOE noted that the actual disposition schedule will likely be a carefully negotiated schedule with the Russians, analogous to the Start II negotiated schedule.

How this process is perceived by non-nuclear states is driven more by when we start plutonium disposition than how long it takes to complete disposition. We should start as soon as possible, and the process should not exclude continued parallel approaches or phased approaches as new technologies are developed. Completion of the disposition mission in both countries is also urgent from an international security standpoint.

The group noted the great difficulty of projecting impacts of low levels of radiation exposure to workers. While the group clearly agrees that plutonium disposition activities should be required to meet existing standards, they urged that DOE be cautious about using ICRP and NCRP recommended models, developed for setting standards, to project actual impacts since these models are conservative and not intended for this use.

The group expressed several concerns regarding disposition activities in Russia:

It was noted that the National Academy of Sciences report has spoken -- the presence of these materials is a "clear and present danger" -- but neither nation appears to be acting that way.

Plutonium Immobilization Alternatives

Questions were raised about whether the Can-In-Canister approach could meet the spent fuel standard, because it eliminates the need for reprocessing to recover the plutonium. DOE indicated that they had not yet concluded whether it does or does not meet the spent fuel standard.

The group urged that the responsibility of the group working on the Can-In-Canister option to evaluate adherence to the spent fuel standard not be diluted by any transfer of that responsibility to a "red team". Such responsibility should not be transferred, but the "red team" should do an independent evaluation of the issue. The group has concerns about the composition of the "red team", and about whether one can get an unbiased and independent view from the team, particularly if it includes people who are involved in one or more of the alternatives.

One benefit of the introduction of fission products as a radiation barrier is that it is an aspect of security that can be discussed publicly. Some other barriers are such that public discussion itself can decrease their effectiveness. The entire process thus far has been conducted in an open way, and if this "red team" operates out of the public view, the credibility of the entire process and its results may be questioned.

The "red team" may be a good idea, but be careful to select people who are independent, balanced, and concerned about getting the best answer. DOE noted that the "red" team will not come up with a go-no go decision on any alternative, but will conduct an evaluation of each alternative. They will develop scenarios related to both the process and the final form, and will point out weak links.

Three of the four immobilization areas selected by DOE to "emphasize" involve Can-In-Canister. If it turns out that Can-In-Canister does not meet the spent fuel standard, then it should be eliminated. That would eliminate three of the four vitrification options, and leave the "vitrification with adjunct melter" as the only vitrification approach to emphasize.

Even though phosphate glass ranks third in the multi-attribute utility analysis, it is not being pursued because it is corrosive. The group asked: if corrosiveness was not one of the criteria used in the multi-attribute analysis, how do we know that there are not other important criteria that were also left out of the analysis? DOE replied that there is not an absolute way to know, but the criteria were developed with the help of an international team with a great deal of expertise in these areas.

Additional Points on Immobilization

U.S./Russian Joint Work

The group was pleased to see very significant progress on the joint work with Russia. This work is important, and DOE is urged to keep this joint work going after the current reports are finished in June. These studies should be followed by joint research and development work, which the countries can use to jointly evaluate options, and to provide a basis for political leaders to make decisions.

Deep Borehole Disposition

The recent work done by DOE and presented at this meeting showed that the technical basis for this option may be stronger than the group had recognized. However, it has not yet been determined whether it meets the spent fuel standard; and there are still very serious questions about the ability to site, and the ability to license, a deep borehole, especially in light of our experience with high level waste siting efforts. Each case has been a highly emotional and political issue, and unreasonable standards have been applied. The time required for site selection and licensing is an important consideration, and will likely make this option non-viable.

DOE noted that this is the only alternative that does not eventually rely upon a high level waste repository. All the other alternatives have at least some high level waste that must be disposed of in another way.

If this option is pursued, it should also be examined regarding its impact on the Yucca Mountain Project and the Waste Isolation Pilot Project.

The following members attended the February 1 and 2, 1996 Senior Technical Review Group meeting in Washington, DC:

Draper, Fry, Kennedy, Kratzer, Muntzing, Nelson, Roessler, Taylor, and Woodfin